2 Are Connected to the Access Road, With the Note that the Main Project Has Been Completed

Early August is marked by elaborate undertakings on the huge land plot in Pampas. The new stadium with the academy is going to be located there. We received 3 planning permissions, 2 of them being for the access road and the earthwork.

After removing the vegetation on the plot, it’s time to remove the upper layer of the humus and adding the gravel one, which is 1 meter tall. The total area is 45,000 m3 for material removal and a staggering 155,000 when it comes to adding the gravel.

 

 

Citizens are Asked for Patience

 

That endeavor should last 2-3 months, where more than 75 trucks will transport material during the day hours. We kindly ask the local citizens to be patient while we engage in that task.

 

These projects should be done by June 2020, when Osijek will play their matches in a wholly new stadium, where a state-of-the-art comfort and ambience will reign.